Construction work news

Hero Image

07.06.2024Evelyn Ýr

It has long been decided to build a house for the exhibition. This winter, we purchased a beautiful timber house in units, which arrived at the site in early May and is awaiting assembly. The process of applying for the building permit has been long and arduous, and in my opinion, far too complicated and not at all transparent. But finally, we obtained the permit and all the necessary documentation, and the only thing left was to have the building inspector come and mark out the foundation. Then a violent storm hit at the beginning of this week; it snowed an incredible amount, and we farmers had our hands full trying to save the livestock. We were lucky not to have laid the foundation earlier, as it would surely be full of snow now.

So we must continue to be patient, allow the soil to dry and settle, and move forward. It looks like the opening of the exhibition will be later as expected, but I am hopeful that it will be no later than this fall.

In the picture, you can see the building materials on the first day of the storm.


SOCIALS

CONTACT

Lýtingsstaðir, 561 Varmahlíð.
Phone: +354 893 3817
[email protected]

SOCIALS->

CONTACT->

Lýtingsstaðir, 561 Varmahlíð.
Phone: +354 893 3817
[email protected]

Soknaraetlun